Project information
Test Piles: 1 no shaft grouted barrette 1,0m x 2,8m, 80m deep, O-cell test max loading 8950 tons
1 no plain barrette 1,0m x 2,8m, 85m deep, max loading 7825 tons
Mass Piling: 28 nos shaft grouted barrettes 1,2m x 2,8m, 85m deep
63 nos plain barrettes 1,0m x 2,8m, 85m deep
21 nos plain barrettes 1,0m x 2,8m, 90m deep
14 nos plain barrettes 1,2m x 2,8m, 85m deep
9 nos plain barrettes 1,2m x 2,8m, 87m deep
8 nos plain barrettes 1,2m x 2,8m, 90m deep
Project description
Upon completion in 2018, Landmark 81 Tower will be the tallest tower in Vietnam. BSV successfully applied O-cell tests for two trial barrettes with record max load of 8 950 tons.
BSV completed the construction works two weeks ahead of the contract program deadline.
Project size: 81 storey building + 3 level basement
Project location: 720A Dien Bien Phu Street, Binh Thanh Dist, Ho Chi Minh City
Client:
Vingroup
Engineer:
Ove Arup & Partners
Hong Kong Ltd.
& Arup Vietnam
Year:
2015